Managing and controlling labor force in construction projects: a brief note from the project controls perspective

Published by Massimoluigi Casinelli on

A unique system serving the needs of stakehoders

About this post

Managing and controlling labor force is crucial for contractors (main and general contractors), as well as for projects’ Owners. Each of this subject has its own specific needs that must be satisfied. Moreover, labor effort is the most variable and uncertain parameter in cost estimating, hence managing and controlling labor force is a fundamental element in cost controls, as well in schedule control and, ultimately, in contract management.  

I describe three situations: contractors and sub-contractors who manage their own labor force. Main or general contractor which do not have a direct-labor force, apart the construction management personnel, and projects’ Owners who needs to monitor labor force to assess the progress of their projects, and particularly the affordability of the estimates to complete (remaining durations of activities). A unique and consistent system can only be designed by the Owner, well in advance of the tender phase, as it must be included in the instructions to bidders and into contractual specifications. This system is part of the more general project controls system.

Contractors managing their own labor force

As a contractor, managing and control your labor force is a primary need.

Usually direct costs estimates take into consideration three main cost categories:

  • Materials
  • Equipments
  • Labor

The key concept is that estimating labor effort is the most variable parameter among the others; In construction works, labor can be 30/40% of the total direct cost.

Managing and control your labor force entails two aspects:

Productivity
  • Estimating, measuring and controlling productivity: units of works produced / units of time (example: 15 cubic meters per hour)
  • Planning, monitoring and controlling labor usage (units of resources in the units of time) assigned to execute tasks; “usage” usually is spread for discipline and craft; resources “usage” has a “profile”.

Measuring and controlling labor is absolutely needed, as the estimate of labor effort and resources usage is the most variable element of a construction costs estimate, hence, of the project budget. Planning and estimating labor force is therefore a key factor in project planning.

Let’s do an example: considering that labor (manpower) is 30/40% (let’s take 35%) of your total cost, so if you spend more hours, let’s say 25% more than planned (due a poor productivity and/or to an underestimate of labor resources usage), the impact on your budget will be 0,35×0.25 = +8.75%, this means that if your expected profit was 10%, now it is reduced to 1,25%!

So, managing and control of labor force (as above described) is a key factor for Cost and Time controls.

Poor labor productivity, as well as underestimates of labor units, lead to delay in project execution, which may cause heavy consequences and financial loss, until bankrupt. In fact, in this case, you will have other costs associated with the breach of contract: liquidated damages.

I have seen a case of liquidated damages caused by a poor planning and estimates of the resources required to execute 50.000 square meters of brick walls in the time-frame required by the project schedule, which needed to works simultaneously on multiples-fronts.

Managing and controlling labor force as a main or general contractor.

Labor force in construction

The above description regards the case of a contractor with “direct” labor force.

A large main contractor or a general contractor do not need to manage “their” direct labor force, as they manage usually sub-contracts assigned to various contractors of services and works. They need to control labor force provided by subcontractors in terms of timely mobilization of labor force and productivity, but in order to get these information, they should transfer theit requirements into the contracts specifications, otherwise they won’t be able to monitor and control “labor force” during project execution and risk of claim increases.

Managing and controlling labor as a project’s owner.

Similarly, Owners (at least the advanced Owners) have all the interests that their contractors manage effectively their costs, to protect their investment. This entails a system to manage labor-hours and productivity. On the other hand, this concept is at base of the development cost/schedule control systems criteria C/SCSC in early ’60 age, (still a revolutionary concept for many companies nowadays), later evolved into EVM (earned value management) and EVMS (earened value management systems). EVM can be applied to resources, and particularly to “labor” to get a measure of productivity. Therefore, projects’ Owners should write contractual specifications to impose to contractor the use of specific methods to collect, analyze and report labor data in construction project. An easy way is to set up a mechanism of payment linked to a performance indicator, like earned value, calculated in hours, which are easily linked to Labor force. The progress payment would be based on a physical progress of work packages, summarized through manhours to calculate EV (in hours). The progress payment is then calculated as EV/Total budget man-hours.

If you are interested in cost engineering and project controls You may follow: My blog “Beyond project controls” – Massimoluigi Casinelli

If you are interested in training on project management / controls, see my courses here or contact me for a tailored course.

Categories: General

Massimoluigi Casinelli

I am a chartered civil engineer and certified CCP (cost engineering and total cost management) at AACE International, with thirty years of experience in project management of the construction sector. I deliver expert planning, programme management and project controls on multibillions-Euro infrastructure programmes, including highways and railways, metro, air terminals and complex buildings (commercial, residential, schools), with some experience in oil & gas and power. I worked in advanced contexts of project management (from matrix organizations of EPC contractors to large employers organized to manage complex capital projects), by undertaking various roles in the field of project management / controls and contract management; this diverse range of experiences allowed me to gain knowledge on the various components of project controls (schedule, cost estimating, budgeting and cost control, progress and performance measurement, risk and claim management). I am an Italian citizen, currently in Italy.